Answer:
B) Individual differences in perception
Explanation:
We all perceive things differently than other people, or in other words, we all see thing differently than other people. Depending on our mood and where we actually are, we perceive things differently. We also have the tendency to fill in blanks with some preconceived ideas, e.g. a person that suffered a prior accident will immediately imagine an action sequence resembling their own experience and will combine it with what they actually saw.
Answer:
Total of Xavier's share = $49750
Explanation:
The allocation of net income to both Xavier and Yolonda will be as follows,
Net Income 90000
<u>Interest on Capital:</u>
Xavier(0.15 * 100000) 15000
Yolonda(0.15 * 50000) <u> 7500</u> <u> (22500)
</u>
67500
<u>Salary:</u>
Xavier 22000
Yolonda <u>20000</u> (<u>42000)</u>
25500
<u>Share of remaining profit:</u>
Xavier 12750
Yolonda <u>12750</u> <u>25500
</u>
<u />
Total of Xavier's share = 15000 + 22000 + 12750 = $49750
Answer:
IRR is greater than required return by 17.38 - 16.8 % = 0.58 %
so project will accept
Explanation:
given data
initial cost = $38,000
cash inflows year 1 = $12,300
cash inflows year 2= $24,200
cash inflows year 3 = $16,100
rate of return = 16.8 %
solution
we consider here IRR is = x so
present value of inflows is equal to present value of outflows .............1
we can say that it as
initial cost = present value
3800 = 
solve it we get
x = 17.38%
here IRR is greater than required return by 17.38 - 16.8 % = 0.58 %
so project will accept