Help will mark brainlyest

Mathematics
2 answers:
Karolina [17]2 years ago
7 0

Answer:

  • 4x - 3
  • 5x - 3

Step-by-step explanation:

  • m∠BEC = (2x+3)
  • when x = 30°
  • m∠BEC → (2(30)+3) → 63°

m∠AED = (360-2(63))/2

m∠AED = 117°

solve for first:

(4x - 3)

(4(30) - 3)

117° ............matches.

solve for third:

5x - 33

5(30) - 33

117° ........matches

Hence the first option and third is correct. rest two are wrong.

Naily [24]2 years ago
5 0

Step-by-step explanation:

BEC is 63° so aed is 4x - 3 I'm ps

You might be interested in
A bad of marbles contains 2 blue marbles and 8 yellow marbles, what is the probability of randomly selecting a yellow marble
Y_Kistochka [10]

Answer:

80% probability

Step-by-step explanation:

Since there are 8 yellow marbles out of 10 marbles in all, that equals 8/10 which is the percent of 80.

5 0
3 years ago
Please Help With My Scatter Plot
valina [46]

Answer:

a

Step-by-step explanation:

idk

6 0
3 years ago
There are four steps in the manufacturing process of a stuffed toy: cutting, stuffing, sealing, and packaging. There are two emp
Anit [1.1K]

Answer:

(a) 2min/15units

(b) 1min/20units

(c) The bottleneck stage is cutting. The process capacity is 450units/hour

(d) The capacity of the new employee should be 1unit/2sec. The process capacity will increase four times

Step-by-step explanation:

(a) Cycle time for stage cutting for 2 employees = 16sec/2units × 1min/60sec = 2min/15units

(b) Cycle time for stage sealing for 1 employee = 3sec/1unit × 1min/60sec = 1min/20units

(c) Process capacity of stage cutting = 15units/2min × 60min/1hour = 450units/hour

(d) If the capacity of the new employee is 1unit/2sec, the process capacity = 1unit/2sec × 3600sec/1hour = 1800units/hour. The process capacity increases 4 times (1800/450 = 4)

7 0
3 years ago
Antonio is buying a stereo, speakers, and amplifiers for his car audio system. He is choosing among 4 models of stereos and 3 st
Jobisdone [24]

Answer:

The answer is 3 or B

Step-by-step explanation:

8 0
3 years ago
Read 2 more answers
What is the remainder when (4x3 + 2x2 − 18x + 38) ÷ (x + 3)?
oksian1 [2.3K]

Answer: A

Step-by-step explanation: I use synthetic division for problems like these:

-3 | 4 2 -18 38

     4 -10 12 2

Since -3 + 3 = 0, we use -3 in this process. Write out the coefficients in order separate from -3. Next, bring down the 4 and multiply -3 by 4 = -12. Add 2 and -12 = -10. Multiply -10 by -3 = 30. Add 30 to -18 to get 12. Multiply 12 and -3 = -36. Add -36 and 38 = 2

4 0
3 years ago
Other questions:
  • Kate used 6.15 meters of ribbon to make bows. How many centimeters of ribbon did she use? 61.5 centimeters 0 0.615 centimeter 6.
    11·1 answer
  • PLEASE HELP ME AND WRITE IN SIMPLIFIED FRACTIONS PLEAAAASSSSSEEE
    7·1 answer
  • James has 16 balloons. 1/4 of his balloons are red. how many red balloons does he hav
    14·2 answers
  • Question 20 of 21
    13·1 answer
  • One number is 2 less than a second number. twice the second number is 2 less than 3 times the first. write two equations to repr
    9·1 answer
  • The regular price for admission to the
    8·2 answers
  • What equation(s) represent joint variations? check all that apply c=2pi z=3x/y y=3x+2 w=abc/4 v=lwh
    7·1 answer
  • Which pictures below show pure substances?
    9·1 answer
  • 40 POINTSSS PLEASE HELPP!!
    15·1 answer
  • Ken is making trail mix for his next hiking club meeting. He mixes 2 pounds of peanuts, 2
    11·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!