Answer: Price, Product, Promotion and Place.
Explanation:
Answer: Project manager
Explanation:
A project manager is a qualified person in the field of project management. Project managers are responsible for the planning, directing, procurement and the execution of a project. Project managers are the first point of contact when issues arise from various departments in the organization before the problem reaches higher authorities.
The project manager is responsible for project management. The project manager does not really take part directly in the things done to produce the end result, but makes sure there is progress and fulfillment of the organizational goals.
Answer 94 districts.
In the federal court system's present form, 94 district level trial courts and 13 courts of appeals sit below the Supreme Court.
Answer:
About 250 ; 2000 bicycles
Explanation:
Opportunity cost simply means the loss incurred on a certain option when the alternative opruoonos chosen.
The opportunity cost of increasing shoe production from 10,000 to 20,000 pairs
The value of 20,000 (x axis) on the y axis is about 3750
Value of point A in the y - axis = 4000
Hence opportunity cost = (4000 - 3750) = 250 bicycles
B.)
The opportunity cost of increasing shoe production from 50,000 to 60,000 pairs
The value of 60,000 (x axis) on the y axis is about 0
Value of point B in the y - axis = 2000
Hence opportunity cost = (2000 - 0) = 2000 bicycles