Answer:
c. 5
Explanation:
L Q MPL (ΔinQ/ΔinL) VMPL
4 52
5 60 8 80
6 66 6 60
7 70 4 40
8 72 2 20
Note: Labour hired per day = L, Total product = Q, Marginal Product of labor=MPL, VMPL =Price*MPL
A firm will maximize the profit by increasing the number of labor as long as VMPL is higher than or equal to the wage rate. In this case, we observe that VMPL ($80)>wage rate ($75) for L=5 but VMPL ($60)<wage rate ($75) for L=6. So, the optimal number of labor to be hired is 5.
Answer:
The answer is c. remains constant in total with changes in the level of activity.
Explanation:
In a cost structure of a firm, for decision-making purpose, it is usually divided into fixed cost and variable cost.
Variable cost is the type of costs which will increase following an additional production of an extra unit of product/service, that is, level of activity has been risen up given the production is taken place. A good example of these cost are material cost, labeling cost.
Fixed cost, as it name may tell, is costs that are unchanged regardless of a firm's activities level. That is, regardless of how many product/service is produced, these costs remain the same. A good example of these cost are depreciation cost, rental cost.
Answer:
The theory which explains the phenomenon described in the question is referred to as "Dividend Signaling".
Explanation:
When a company announces that is will be paying dividends, stock market players percieve this as an indication of :
- Strenght
- Performance and
- Profitability.
Hence investors will find it more attractive to purchase such a stock.
Cheers!
Thank you for posting your question here at brainly. I hope the answer will help you. Feel free to ask more questions.
The strength of bargaining power forces depends on the availability of substitutes and <span>the relative size of the firm </span>compared to the size of suppliers or customers.
Answer:
The correct answer is A that is late start date.
Explanation:
Late start date is the filed which comprise of the latest date on which a task could be started without delaying the finish of the project.
The date is grounded on the date when the task is started and also on the late start of the task, late finish dates of the tasks predecessor and the successor as well and also on other constraints.
So, the late start date for the activity is the latest possible time.