Answer:
a. $21 per machine hours
b. $4,855
Explanation:
a. The computation of the plantwide predetermined overhead rate is shown below:
Plantwide predetermined overhead rate is
= Variable overhead cost rate per machine hour + Fixed overhead cost rate per machine hour
= $2 + (fixed manufacturing overhead cost ÷ Estimated machine hours)
= $2 + ($4,275,000 ÷ 225,000 machine hours)
= $2 + $19
= $21 per machine hour
b. Now the total manufacturing cost assigned is
Particulars Amount
Direct material $1,702
Direct labor $1,221
Variable manufacturing overhead $168
(84 × $2)
Total variable cost $3,091
Add:
Fixed manufacturing overhead
(84 × $21) $1,764
Total manufacturing cost assigned
to Job P90 $4,855
Answer:
The answer is trade fixtures
Explanation:
Trade fixtures are a tenant's installments which become a part of the land during the leasing contract period but they are not belong to the landlord thereafter. The tenant reserves the right to remove the the installments at the end of the contract term.
Answer:
The most the firm can spend to lease the new equipment without losing money=$75,000
Explanation:
The point at which the revenue in terms of sales equals the cost is the break-even point. This can be expressed as;
R=C
where;
R=revenue from sales
C=cost
And;
R=P×N
where;
R=revenue from sales
P=price per unit
N=number of units
In our case;
P=$7.5 per unit
N=10,000 units
replacing;
R=7.5×10,000=$75,000
Total revenue from sales=$75,000
C=p×n
where;
p=cost per unit
n=number of units
In our case;
p=$5
n=unknown
replacing;
C=5×n=5 n
At break-even point, R=C;
5 n=75,000
n=75,000/5=15,000
The break-even cost=5×15,000=$75,000
The most the firm can spend to lease the new equipment without losing money=$75,000
no they should not 100% correct
Answer: response
Explanation: she responded to the advertisement