Answer:
A project team is a team whose members usually[quantify] belong to different groups, have different functions and are assigned by the project manager to activities for the same project. A team can be divided[by whom?] into sub-teams according to need. Usually project teams are only used[by whom?] for a defined period of time. They are disbanded[by whom?] after the project is deemed[by whom?] complete. Due to the nature of the specific formation and disbandment, project teams are usually in organizations.
Explanation:
mark me as brainliest
Answer:
$1,000
Explanation:
We know that
Total cost = Fixed cost + Variable cost
From the data given, we can calculate the variable cost using the high-low technique.
Variable cost per unit
=
=$15
Lease cost = FC + $15(Machine hours)
Lease cost -$15(Machine hours) = FC
Case,
i) 800 machine hours,
FC = Lease cost - $15(Machine hours)
= $16,000 -$15(1000) = $1,000
Answer:
The amount of overhead debited to Work in Process Inventory should be: a. $182,00
Explanation:
The Overheads are Applied in the Manufacturing Costs as:
Budgeted Rate × Actual Activity for the Month
At the End of the Period we would need to determined whether this amount of overhead is Over or Under Applied by comparing it to the actual overheads incurred of $180,000 (given)
In our Case, the predetermined overhead rate is 70% of direct labor cost
<em>Thus we need to find the Direct Labor Cost first</em>:
Total Labor Costs $360,000
<em>Less </em>Indirect Labor Costs<em> </em>$100,000
Direct Labor Cost $260,000
<em>Therefore Overheads applied would be determined as:</em>
= $260,000 × 70%
= $182,000
Answer:
$55,000
Explanation:
The opportunity costs corresponds to the benefits an investor loses when opting for one alternative over another. In this case, assuming Paula has to quit her job in order to start the new business, the opportunity cost is her current salary since this is the only "benefit" she would miss by starting the new business. Therefore, the opportunity cost is $55,000.