I need help on this please​

Mathematics
1 answer:
frez [133]1 year ago
6 0

Answer:

only C is a function cause a function has only 1 same value.

You might be interested in
Try the following word problem using GRASP strategy
andrew11 [14]

Answer:

.

Step-by-step explanation:

3 0
2 years ago
Can someone please be nice enough and give me all the answer for these questions.
PSYCHO15rus [73]
1. 1/9 since you take all the "a"s in the words which is 2/18
2.2/9 same thing as above
3.18/18 since there is no "O" it's a trick question
4.3/9
5.5/6 since you don't count 6
6.1/2 and 1/2 coins are always 1/2 unless you flip twice
7.5/13
8.1/2 because 1,3,5 odd 2,4,6 even 
Hope that helps
8 0
2 years ago
1 and 5/6 + 2 and 2/11
lions [1.4K]
1 \frac{5}{6} +2 \frac{2}{11} =\frac{(1\times6)+5}{6} +\frac{(2\times 11)+2}{11} =\frac{11}{6}+\frac{24}{11} \\\\=\frac{11\times 11}{6\times 11} +\frac{24\times6}{11\times6} =\frac{121}{66} +\frac{144}{66}=\frac{121+144}{66} =\frac{265}{66}\\\\=\boxed{\bf{4\frac{1}{66}}}
3 0
3 years ago
PLEASE HELP!!! WILL GIVE BRAINLIEST IF YOURE RIGHT!!!!
Svetllana [295]
D. is the answer

y - y1 = m(x - x1)
the slope is 2/3, so choose which point to be (x1, y1)
5 0
3 years ago
The Sureset Concrete Company produces concrete. Two ingredients in concrete are sand (costs $6 per ton) and gravel (costs $8 per
Maksim231197 [3]

Answer:

The Sureset Concrete Company

The tons of gravel and sand that should be purchased each day are:

Sand = 800 tons

Gravel = 700 tons

Step-by-step explanation:

Two ingredients for producing concrete = sand and gravel

Cost of sand per ton = $6

Cost of gravel per ton = $8

Sand and gravel = 75% of the concrete

Therefore 25% (100 - 75%) will be made up of cement and water

Tons of concrete produced each day = 2,000

Sand and gravel = 1,500 (2,000 * 75%)

Sand <= 40% of 2,000 = 800 tons

Gravel => 30% of 2,000 = 700 (1,500 - 800) tons

To minimize costs,  800 tons of gravel and 700 tons of sand should be purchased each day.

Total cost incurred daily for both sand and gravel = $10,400 (800 * $6 + 700 * $8)

3 0
3 years ago
Other questions:
  • From 6 p.m to 6 a.m. the temperature dropped 1.4 degrees each hour. what was the total change in temperature between 6 p.m. and
    6·2 answers
  • Three times a number minus 2 is 25. What is the number?
    13·2 answers
  • Use synthetic division to solve (4x-3x+5x+6)/(x+6). What is the quotient?
    13·1 answer
  • Antony and Lily started moving in opposite directions from the same point at the same time. If Antony was biking with average 12
    14·1 answer
  • Pls answer this and thank you
    11·2 answers
  • solve x^2-8x=20 by completing the square. Which is the solution set of the equation? a {2, 10} b {-2, 10} c {2, -10} d {-2, -10}
    7·1 answer
  • How would figure out if a equation has one answer,zero answers,or infinite. Like a equation like 3(x+9)=3x+27
    13·1 answer
  • A number cube has 6 different faces, numbered 1 to 6. All faces have an equal probability of being rolled. What is the probabili
    6·1 answer
  • There are 45 people on the bus. 60% of them were adults. How many adults were on the bus? Write an explanation
    8·2 answers
  • When sketching a parabola, use ______ to make both sides even and avoid extra calculations.
    15·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!