<u>Answer: </u>Option B
<u>Explanation:</u>
In this case Alber Miano had created replica of the invoices and has forged the contractor's signature. The hours of the trade contractors work was changed slightly. Due to the failure of the internal controls Miano was able to indulge in fraudulent activities in a bolder manner.
Through an internal audit Miano's activities were found out by the auditor and the vice president. Then Miano accepted that he was guilty and only showed less than half the amount spent on tangible assets from the accumulated fraudulent activities for four years.
<span>It seems as though Maria needs to interview more people to get the best representatives for her study. a good strategy would be to screen representatives first by giving them a written test to see if they would even be close to what she was looking for then from those written tests she could choose who to interview and the interview could be shorter because a lot of information she would have discovered by the written test.</span>
The statement that does not refer to the reason that aids in project crashing is
(D) there are no critical activities that can be crashed further.
Explanation:
Project crashing basically refers to the method by which the duration of the project is reduced .This can be done by
- Reducing the time taken by one or more critical activity
- By devoting more resources in order to complete the project as early as possible.
- The cost associated with the project is also increased
In Crashing,<u> the time is inversely related to the cost of the project</u>.It means that if the time of the project increase then the project cost is reduced and if the time o/duration of the project decrease then the cost involved in the project increases
Answer:
Net Present Value = $660.98
Explanation:
<em>The Net present value (NPV) is the difference between the Present value (PV) of cash inflows and the PV of cash outflows. A positive NPV implies a good and profitable investment project and a negative figure implies the opposite. </em>
NPV of an investment:
NPV = PV of Cash inflows - PV of cash outflow
<em>PV of cash inflow = A× (1- (1+r)^(-n))/r
</em>
A- annul cash inflow, r- 8%, n- 3
PV of cash inflow= 41,000× (1- 1.08^(-3))/0.08
= 105,660.98
Initial cost = 105,000
NPV = 105,660.98 - 105,000
= $ 660.98
Answer: f. Supply of manufactured houses shifts leftward and manufactured houses increase in price
Explanation:
All else being equal, when the price of an input into the production process increases, it makes producing the goods in question more expensive and so producers will respond by reducing production levels to maintain Profitability.
As the price of cement rises, making manufactured houses becomes more expensive and so the makers of manufactured houses will reduce the number of manufactured houses they make. This will reduce Supply thereby shifting the Supply Curve to the left. The new Equilibrium level will indicate a higher Equilibrium price as shown in the attached graph.