Answer:
12 bow ties
Step-by-step explanation:
1/2 yard = 1.5 feet = 1 bow tie
1.5 x 2 = 3 feet
1 yd = 2 bow ties
18/3 = 6 yards
6 x 2 = 12 bow ties
Answer:
f(x+1) = -3/4 × f(x)
Step-by-step explanation:
first of all, the sign of the numbers in the sequence is alternating. so, there must be a "-" involved.
that eliminates the first and third answer options.
and the absolute values of the numbers in the sequence are going down. |f(x+1)| < |f(x)|
that eliminates the fourth answer option, as this says that
|f(x)| < |f(x+1)|. and that is the opposite of how the actual sequence behaves.
Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
D = 1/2 a t^2 is given. And it wants you to find t in terms if a and d. Which means, you need to arrange the equation and let t be alone.
If you let t^2 alone ;
2d/a = t^2
And square root t^2 will give you t ;
SquareRoot(2d/a) = t
The answer is (2)
Answer:
I think this is the answer! 2x3 + 5x2 - x - 6 let me know if it’s right :)
Step-by-step explanation: