Answer:
Losses for the producers of Waterworld, if they finished the movie would be <u>$50 million</u>. If they did not finish the movie, losses would be <u>$130 million.</u>
Explanation:
This is because, the difference between all their expenses in making the movie and the revenue generated is actually <em>$50 million</em>. This happens to be their losses while on the other-hand, if they didn't finish making the movie, it would be <em>$130 million </em>(aside the cost spent in finishing the movie after rebuilding the set)
Feedback Control <span>is a mechanism for gathering information about performance deficiencies after they occur.</span>
Answer:

So option (b) is correct option
Explanation:
We have given value of operation PV = $25.00
WACC, that is
= 11.50% = 0.1150
It is grow at a constant rat of 7 % so g = 0.07
We have to find the value of 
We know that value of operation is given by

So 

So option (b) is correct option
Answer:Self-awareness can help improve your career because it makes it easier to understand how others see you. This is key for success. It's essential to be aware of the perceptions of higher-ups, of course, but it's also important to know how you come off when you're working in a leadership capacity.
Explanation: trust
Answer:
a. 300 units
b. $3,750
c. $3,750
d. 100 units
Explanation:
a. The computation of the economic order quantity is shown below:
=
=
= 300 units
b. For annual holding cost, first we have to find out the average inventory would equal to
= Economic order quantity ÷ 2
= 300 units ÷ 2
= 150 units
Now the Carrying cost = average inventory × carrying cost per unit
= 150 units × $25
= $3,750
c. For ordering cost, first we have to compute number of orders would be equal to
= Annual demand ÷ economic order quantity
= $15,000 ÷ 300 units
= 50 orders
Now Ordering cost = Number of orders × ordering cost per order
= 50 orders × $75
= $3,750
d. The computation of the reorder point is shown below:
= (Annual demand ÷ total number of days in a year ) × lead time
= (15,000 units ÷ 300 days) × 2 working days
= 100 units