Answer:
Price variance will be $4512.5 ( Unfavorable )
Explanation:
We have given standard material cost per yard = $2
Actual material cost per yard = $2.10
Standard yards per unit = 4.5
And actual yards per unit = 4.75
Units of production = 9500
Total number of actual quantity used = 9500×4.75 = 45125
So direct material price variance = ( standard price - actual price ) × actual quantity used = ( $2 - $2.1 ) × 45125 = -$4512.5
So price variance will be $4512.5 ( Unfavorable )
Answer:
Production total cost= $104,400
It is more profitable to buy the product.
Explanation:
Giving the following information:
Production costs (1,000 units):
Direct material $ 45,000
Direct labor $30,000
Factory overhead (30% is variable) 98,000
Buy:
1,000 units from an outside supplier for $100,000.
<u>I will assume that the fixed overhead is not avoidable, therefore it should not be taken into account for the decision making.</u>
Production total cost= 45,000 + 30,000 + (98,000*0.3)
Production total cost= $104,400
It is more profitable to buy the product.
Parametric estimation is a techniques that uses a statistical relationship to calculate cost or duration based on historical data and other project parameters
Parametric estimation is a quantitative method (statisitical relationship) used to estimate the project cost, resources, and duration based on historical data and other project parameters.
Parametric estimation models are used when:
- There is precedent
- The model is a unit hence can be scaled up
- The parameters required are easily quantifiable
While the other options of this question is incorrect because:
b. grass roots estimating
Cost estimation done by the individuals who will be performing the task being estimated.
c. empirical estimating
Estimation method in which the data is obtained using empirical formulas. It is usually based on an amalgamation of historical data, assumptions, guesses, and personal experience.
d. analogous estimating
Also called top-down estimating, this is a technique that involves comparing previous projects, personal experiences and cursory cross-referencing observed costs to estimate time resources required. This technique is most useful in the absence of quantifiable data.
You can learn more about project estimation at
brainly.com/question/24322317
#SPJ4
Answer:
$140,000
Explanation:
The computation of adjusted balance in the Accumulated Depreciation account is shown below:-
adjusted balance in the Accumulated Depreciation account = unadjusted normal balance + Credit Accumulated Depreciation account
= $120,000 + $20,000
= $140,000
Hence the adjusted balance in the Accumulated Depreciation account is $140,000.
Answer:
c. governmental interventions