.....................................................A
Answer:
d. Generates a change in quantity demanded.
Explanation:
Because in this case only the price is changing and all other factors are held constant the demand curve will not move and any movement that will take place will be along the demand curve. If the price increases the quantity demanded will decrease and if the price decreases the quantity demanded will increase, the reason for this is that the demand curve is downward sloping, therefore a price change will only change the quantity demanded.
Answer:
Net market value of firm = $903,196
Explanation:
Items to determine the Market value of the firm are as below
Item Amount
Current value of building $1,440,000
Current value of equipment $467,000
Market value of inventory $205,000
Cash in hand $10,500
98% of debtors $220,696
Less: Owings -<u>$1,440,000</u>
Net market value of firm <u>$903,196</u>
EXPLANATION: The MP curve is one of three related curves used in the analysis of the short-run production so basically the marginal product (MP) curve plays in key role in the economic analysis of short-run production by firm
Answer: MP curve looks like a reverse U shaped curve or are invertedly U-shaped
Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.