Project manager in a functional matrix had more lesser influence over one in a dedicated project team because:
- the dedicated team allows a formal authority over the participants
- the dedicated team offers a greater access to influence currencies than the project manager in a functional matrix.
<h3>Who is a Project manager?</h3>
A Project manager is a manager with the responsibiltiy of planning, organizing and directing the completion of specific projects for such organization.
<em />
In conclusion, in a functional matrix, the manager sdoes compensate for their lack of formal authority by exercising informal influence through the use of relationships and personal <em>currencies.</em>
<em />
<em />
Read more about Project manager
<em>brainly.com/question/6500846</em>
Answer: B
Explanation: Engines for the cars is a cost directly related to the Ford cars being produced. The property taxes and the janitors rates are indirect costs because they are general costs needed to run the business but are not directly linked to the production of the ford cars
Answer:
A Tying Contract
Explanation:
If a seller requires an intermediary to purchase a supplementary product to qualify to purchase the primary product the intermediary wishes to buy, it results in a tying contract. It is mostly treated as an illegal because it pushes intermediary organization to buy other products if they wishes to purchase the products which is actually needed to be purchased. Some companies make it compulsory for their intermediaries in doing so. For example, if you have to buy 10 packs of Lays, then you must be buying 5 extra boxes of Pepsi as well. It is being done because of the power and market share that company is enjoying in the market, so they take its advantage.
Answer:
increase productivity in office setting
Answer:
The correct answer is B.
Explanation:
Giving the following information:
The variable costs are $4.50 per unit. London Plastics sell 15,000 units.
To calculate the total variable costs we need to use the following formula:
Total variable cost= unitary variable cost* total amount of units
Total variable cost= 4.5*15,000= $67,500