Answer:
$
Standard total overhead cost (0.5 hr x 25,000 x $3.29) 41,125
Less: Actual total overhead cost ($21,000 + $18,000) 39,000
Total overhead variance 2,125(F)
Standard overhead application rate
= <u>Budgeted overhead</u>
Budgeted direct labour hours
= <u>$115,150</u>
35,000 hours
= $3.29 per direct labour hour
Explanation:
Total overhead variance is the difference between standard total overhead cost and actual total overhead cost. Standard total overhead cost is the product of standard hours per unit, standard overhead application rate and actual output produced. Actual total overhead cost is the aggregate of actual variable overhead cost and actual fixed overhead cost. Standard overhead application rate is the ratio of budgeted overhead to budgeted direct labour hours (normal capacity).
The employers look for potential employees that they think would be a good fit and have good qualities.
Answer:
FALSE
Explanation:
It is False that the difference between operations and projects is that operations end when their objectives have been reached, whereas projects do not.
The reverse is true because projects are time-bound and they come to an end when their objectives have been achieved, but company operations are expected to continue as a going concern.
A project is an activity to meet the creation of a unique product or service, an thereafter terminates while operations are day to day routine activities that are expected to continue
Answer:
c.Moral hazard
Explanation:
Moral hazard can occur when banks take on excessive risk more than they would normally take on because they know they would be bailed out if they fail.
I hope my answer helps you