Answer:
$0.6 per unit
Explanation:
The computation of the variable rate per unit of output is shown below:
But before that first we have to determine the variable cost which is
= Total utilities cost - fixed cost
= $2,600 - $2,000
= $600
And the number of units produced is 1,000 units
So, the variable rate per unit of output for utilities cost is
= $600 ÷ 1,000 units
= $0.6 per unit
Answer:
a.reduced MI and increases M2
Explanation:
Hope that help you!!
Answer:
c. Marginal cost is $8, and average total cost is $5.
Explanation:
Marginal cost of a firm is the cost difference in producing an additional unit of a firm's output. The extra amount result from the an extra unit of output produced. It is derived by calculating the difference between the total cost and dividing it by the difference in output i.e change in TC/ change in output
In the question, The change in TC is calculated as $5008 - $5000 = $8 and the change in quantity is 1001 - 1000 = 1
Therefore 8/ 1= 8 marginal cost is = $8
on the other hand, Average total cost is the cost per unit of output i.e the cost of a commodity out of all the products produced by a firm. it is calculated by dividing the total cost by the total number of output
In the question above, The total cost is $5,000 and the Total output is 1,000
$5,000/ 1000 =$ 5
similarly, when the total output increased to 1001 and the total cost rises to $5008 the Average cost still remains at$ 5
prove: 5008/ 1001 = 5.0002 which is approximately equal to 5.
therefore the correct answer is c. Marginal cost is $8, and average total cost is $5.
Answer:
A. $549000
Explanation:
Given information
Number of outstanding stock of Sherry, Inc = 60%
The cost of the land = $207,000
Fair value at the acquisition date = $549,000
By considering the above information, the value reflected in a consolidated balance sheet is $549,000.
The historical principle says that the fixed assets should be recorded at the purchase price or acquisition cost only and the same is to be considered
Answer:
The correct answer is letter "B": a duty to discover and remove the hazard.
Explanation:
According to the hierarchy of Hazard Control, there are five (5) layers on determining the actions that should be taken in front of a dangerous situation. Those layers include <em>protecting workers with Personal Protection Equipment (PPE), changing employees' methods of working implementing administrative controls or engineering controls, substituting the hazardous element, or completely eliminate.
</em>
Thus, <em>the elimination or removal of the hazardous element after discovering it is the most effective measure to take to avoid any damages to other individuals, employees or not.</em>