Answer: 22 units
Explanation:
Given
lead time = 7
mean = 15
Standard Deviation = 5
service level = 95%
Using the formulae
Safety stock = safety factor ( z value) x standard deviation x 
But
Z value for 95% service level = 1.645 = safety factor
= 1.645 x 5 x 
=21.76 which estimates to 22units
Well considering they are still juveniles, they haven't really had a chance to go through life. The people "punishing" them don't want to screw their career and life up. So they give them a second chance by rehabilitation process and a chance to wipe that charge off of their record.
Idk...hope this helped!
Goooood luck!
Answer:
The journal entry to record the day's sales would include
Debit Cash $10,648
Debit Cash shortage $32
Credit Sales $10,680
Explanation:
Total Sales is $10,680, so the sales will be recorded by this amount. The cash is $10,648, so it will also be recorded by the same amount. A debit entry will be placed to reflect the effect of this transaction as there is a cash shortage.
Answer:
Wants are requests directed to specific types of items. Demands are requests for specific products that the buyer is willing to and able to pay for. In a consumer market examples are usually very clear to identify.
Answer:
Answer for the question:
Assume that the hypothetical economy of Molpol has 8 workers in year 1, each working 1,200 hours per year (40 weeks at 30 hours per week). The total input of labor is 9,600 hours. Productivity (average real output per hour of work) is $10 per worker
Instructions: In parts a and b, round your answers to the nearest whole number. In part c, round your answer to 2 decimal places.
a. What is real GDP in Molpol? Suppose work hours rise by 2 percent to 9,792 hours per year and labor productivity rises by 5 percent to $10.5
b. In year 2, what will be Molpol's real GDP?
c. Between year 1 and year 2, what will be Molpol's rate of economic growth? percent
Is given in the attachment.
Explanation: