Bingel [31]
2 years ago
10

The critical path of a project includes 45 business days in phase one, 20 business days in phase two, 15 business days in phase

three, and 10 business days in phase four. the workforce is expected to work six days per week. if the project needs to be complete by, if the project started on 2nd january, when is the deadline? do not include any holidays or employee time off.
Mathematics
1 answer:
tester [92]2 years ago
6 0

Using proportions, it is found that the deadline for the project is of April 17th.

<h3>What is a proportion?</h3>

A proportion is a fraction of a total amount, and the measures are related using a rule of three. Due to this, relations between variables, either direct(when both increase or both decrease) or inverse proportional(when one increases and the other decreases, or vice versa), can be built to find the desired measures in the problem, or equations to find these measures.

The number of days they need is:

45 + 20 + 15 + 10 = 90.

The number of weeks they need, considering 6-day weeks, is:

90/6 = 15.

Looking at a calendar, we have that:

  • 4 weeks after January 2nd is January 30th.
  • 8 weeks after January 2nd is February 27th.
  • 12 weeks after January 2nd is March 27th.
  • 13 weeks after January 2nd is April 3rd.
  • 15 weeks after January 2nd is April 17th.

The deadline for the project is of April 17th.

More can be learned about proportions at brainly.com/question/24372153

#SPJ1

You might be interested in
What number should be added to both sides of the equation to complete the square?
baherus [9]
-4 is what you put on both sides Bc it’s half of b
4 0
3 years ago
Look at photo <br><br><br><br><br><br> ————————————————————————
8_murik_8 [283]
Huh what about the photo you gotta b
6 0
3 years ago
7/8 – m = 2/3<br><br> What is the value of m?<br><br> correct=brainliest
AnnyKZ [126]

Answer: the answer is 5/24

Step-by-step explanation:

If you do 7/8 - 2/3 you get 5/24 and to check your work, do 7/8 - 5/24 and you get 2/3

Hope this helps ^^

6 0
3 years ago
Read 2 more answers
Eva is playing a game at the school carnival. There is a box of marbles, and each box has a white, a green, a blue, and an orang
sveta [45]
I think that it is 8
3 0
3 years ago
Read 2 more answers
Which shows the quotient of g and 7?
egoroff_w [7]
The answer is d because quotient means the outcome of a division between two numbers. So therefore it has to be a division equation, which is d.
4 0
3 years ago
Other questions:
  • 4. Which value is a solution to the inequality? 4x − 7 &gt; 5
    11·1 answer
  • Is −10 − 5 equal to −10 + (−5)? Explain in<br> terms of additive inverses.
    14·1 answer
  • Simplify as much as possible:<br> (A^-1B^3)^5
    7·1 answer
  • Helppp!!!!laura is playing a card game with her friend.she will draw two cards from those pictured.
    14·1 answer
  • Sarah has $20 saved. She gets $10 per week for her allowance, and she saves her allowance for the next 3 weeks. At the end of th
    12·1 answer
  • Michaela has h hair ties. Michaela's sister has triple the number of hair ties that Michaela has . Choose the expression
    13·1 answer
  • A major DVD rental chain is considering opening a new store in an area that currently does not have any such stores. The chain w
    10·1 answer
  • PLEASE HELP ASAP! THX IN ADVANCE
    6·2 answers
  • Scientists have put together bones to make a T-Rex skull that has a mass of 600 pounds. They just found a new tooth fossil to ad
    6·2 answers
  • What is the midpoint of the segment shown below?
    12·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!