Answer:
C) 410 tubs
Explanation:
the contribution margin for sinks is $70 (= $150 - $80) and the contribution margin for tubs is $150 (= $600 - $450).
the molding equipment has 4,050 hours of capacity per year, so it can produce either 2,025 sinks or 810 tubs.
we can determine what product is more profitable if we determine a contribution margin per molding equipment usage ratio:
- sink = $70 / 2 hours = $35 per hour
- tub = $150 / 5 hours = $30 per hour
It is more profitable to produce sinks than tubs, but we can sell only 1,000 sinks per year, so even after we product the 1,000 sinks we will have spare molding equipment capacity which we can use to produce tubs.
The spare molding equipment capacity after producing sinks = 4,050 total hours - 2,000 hours used to produce sinks = 2,050 spare molding hours
We can produce 410 tubs (= 2,050 molding hours / 5 hours per tub)
Answer:
Geographic segmentation
Explanation:
it is strategy related to geographic segmentation. it include strategy to provide all those facilities to the customer on the basis of location of customers. As it is given in question Hilton hotels provide more sleeker rooms in northeastern side while more rustic hotels in southwestern hotels.
In generally speaking, geographic segmentation strategy totally based on the preference of targeted customers.
Example of Geographic segmentation approach include large production of raincoats to those areas that experience heavy rainfall etc
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.
D) Checkabe Deposits are assets for the bank
Answer:
B) Your portfolio has a beta equal to 1.6, and its expected return is 15%
Explanation:
Since the correlation coefficient between both stocks X and Y is zero, when one stock has an expected return a little higher than 15%, the other stock will have an expected return a little lower than 15%, so both variations basically cancel out each other. So the average expected return for both X and Y will be 15%.