she has $60 left.

she can afford 3 more months of her gym membership.
Answer: the due date would be 92 weeks
Step-by-step explanation:
Since the time required to complete a project is normally distributed, we would apply the formula for normal distribution which is expressed as
z = (x - µ)/σ
Where
x = number of weeks.
µ = mean
σ = standard deviation
From the information given,
µ = 80 weeks
σ = 10 weeks
If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, the z score corresponding to 90%(90/100 = 0.9) is 1.29
Therefore,
1.29 = (x - 80)/10
x - 80 = 1.2 × 10
x - 80 = 12
x = 80 + 12 = 92
Answer:
45
Step-by-step explanation:
45+45=90
ABE = 90 degrees
So if ABE is 90 degrees, then ABE (90) minus DBE(45) = ABD(45 degrees)
Hope you have a great day friend! <3
It's a bit of a trick question. The principal square root of a real number, as indicated by the radical sign, is never negative. So if p is negative we'll get -p as the result. We write this with absolute value: