Answer:
The correct option is A
Explanation:
Transaction costs are the whole array of costs associated with selling, buying, transferring goods etc.
Transaction costs can be of different types which are:
- search costs
- monitoring costs
- Bargaining costs
- transfer costs etc.
Answer:
Identify the sequence of tasks that take the longest to complete
Explanation:
Program Evaluation and Review Technique (PERT) is a project management tool that is used to manage potential contingencies in the process of executing a project. It is used to schedule ,organize and coordinate tasks in a project.
Determining the critical path on a PERT network lists out the time required for different tasks to be completed and as a result , the sequence of tasks that require the longest time are identified.
Total cost per week = $3600
The correct option is <u>C.$3,600</u>.
<u>Explanation</u>:
<em><u>Given</u></em>:
Cost for constructing and purchasing the equipment for restaurant = $520,000
Minimum return = 10% of investment
Restaurant is opened = 52 weeks per year
No. of meals = 900 meals/per week
Cost of meal = $5
Expense for material and electricity= $600
Expense for weekly wages = $1000
Fixed cost per week = ([520,000(.10)]/52) + 1000 = 2000
Variable cost = 1000 + 600 = 1600
Total cost = Fixed cost per week + Variable cost
= 2000+1600 = 3600.
Total cost per week = $3600
The price of the bond is $100.
The bond's price is the present value of the face value plus the present value of the interest accrued throughout the bond's term.
The coupon interest rate is 5% of 100, that is $5 per year. The yield to maturity is also 5%. Because the coupon rate is equal to the yield, the bond's present value will only be its face value.
Present value = 5(P/A, 5%, 2) + 100(P/F, 5%, 2)
= 5×1.85941+ 100×0.90703
= 100
Therefore, the price of the bond is $100.
To know more about price of the bond click here:
brainly.com/question/15567868
#SPJ4
Answer: 204.76%
Explanation:
In the earlier scenario, furniture maker manufactured 47 (42 non defective) pieces per 5 laborers working 8 hours day.
Thus, the productivity in terms of units per labor hour is as follows:

= 1.05
Similarly, after the process improvement, the productivity in units per labor hour would be:

= 3.2
Thus change in productivity would be calculated as:

= 2.047 × 100
= 204.76%
Thus, the productivity of non defective parts would increase by 204.76%.