Answer:
See below
Explanation:
1. Predetermined overhead rate
= Total fixed overhead cost for the year / Budgeted standard direct labor hour
Predetermined overhead rate = $530,400 / 68,000
Predetermined overhead rate
= $7.8 per direct labor hour
2. i. Fixed overhead budget variance
= Actual fixed overhead - Budgeted fixed overhead
= $521,000 - $530,400
= $9,400 favourable
ii Fixed overhead volume variance
= Budgeter fixed overhead - Fixed overhead applied to work in process
= $530,400 - (66,000 × $7.8)
= $530,000 - $514,800
= $15,200 unfavorable
Answer:
Following are the solution to this question:
Explanation:
Please find the complete question in the attachment file.
Applied to fixed overhead
Overhead fixed by DL hr.
DL hours standard
Application of fixed overhead
Variance in volume
Application of total fixed overhead
Fixed total estimates Superfast
Variance of volume
Answer:
Maximize 30A + 40B.
Explanation:
Given that
Profit margin of product A = $30 per unit
And, the Profit margin of product B = $40 per unit
And, let us assume that
Number of product A produced is A
And, the Number of product A produced is B
So, the total profit is
= 30A + 40B
And, this reflects the maximum profit
All other information which is not given is not relevant. Hence ignored it
Elephant I would guess........
Answer:
Gary's Basis in the partnership interest is $155,000
Explanation:
Particulars Amount ($)
Adjusted Basis Of Land 250000
Mortage*Share In Percentage ($200000*50%) (100000)
Additional Borrowing*Share In Percentage ($50000*50%) (25000)
#Difference*Share In Percentage ($100000-$40000)*50% 30000
Basis 155000
Difference:
Net Income 100000
Distribution Of Each Partner*2 ($20000*2) (40000)