Answer:
C. negotiating contracts
Explanation:
Discussing and Compromising on contract term in order to reach out final agreement between the company management and union at Selzar Inc.
The correct answer is C. remains constant
If production costs for both are equal, then it is completely the same what the demand is great for, since the cost will always be the same for them. If people want 3 cars and 2 trucks, it will be the same as if they wanted 4 trucks and 1 car.
Answer:
15.83%
Explanation:
Calculation to determine is the standard deviation of the returns on Kurt’s Adventures, Inc. stock
First step is to determine l E(r)
E(r) = (.30 *.30) + (.55 *.12) + (.15 *-.20)
E(r)= .09 + .066 -.03
E(r)= .126
Second step is to determine Var
Var = .30 *(.30 -.126)^2 + .55 *(.12 -.126)^2 + .15 *(-.20 -.126)
Var=0090828 +.0000198 + .0159414
Var= .025044
Now let determine the Std dev
Std dev = √.025044 = .15825
Std dev= 15.83 percent
Therefore the standard deviation of the returns on Kurt’s Adventures, Inc. stock.is 15.83 percent
Question: The question is incomplete. See the full question below and the answer.
You are an up-and-coming developer in downtown Seattle and are interested in constructing a building on a site you own. You have collected four bids from prospective contractors. The bids include both a cost ($millions) and time to completion (months):
Contractor Cost Time
A 100 20
B 80 25
C 79 28
D 82 26
The problem now is to decide which contractor to choose. B has indicated that for another $20 million, he could do the job in 18 months, and you have said that you would be indifferent between that bid and the original proposal. In talking with C, you have indicated that you would just as soon pay her an extra $million if she could get the job done in 26 months. Who gets the job? Explain your reasoning. (It may be convenient to plot the four alternatives on a graph.)
Answer:
See the explanation for the answer and find attached of the graph.
Explanation:
So we draw a regression line of Time vs Cost and best fit a curve based on the data given, given in the above figure. The four alternatives are marked in the figure as well. Our main objective is to reduce both time and cost, but that might not be possible So the best thing would be to look for alternatives which lie below the line. If C gets an extra million, then that point would come below the regression line, and it would be a better alternative than D, because for the same time we are getting the job done at a cheaper cost.
Also if B is paid extra 20 million, that point also comes below the regression line, and hence will be a better alternative than A because for the same cost again we are getting the job done earlier. We need to choose between B and C. Now in order to optimise both cost and time, we need to choose a point close to the middle point of the regression line segment in 1st quadrant. We see that C is much more closer to the middle point and hence seems like a better option.
So we choose C as our contractor if we consider B's alternative bid, but if we do not consider B's alternative bid and stick to the original one, we choose B as our contractor.
<span>Working with an Entrepreneurial Attitude is a ... of today’s fiercely competitive ... associated with risk as your entrepreneurial attitude grows ...</span>