Traditional project management focuses on thorough planning up front. Such planning requires predictability.
The traditional project management is a practice which includes a set of developed techniques which are used in order for planning, execution, monitoring, closure, and estimating. Here the projects are run in a sequential cycle.
The planning which is done in traditional project management, this planning requires predictability. Thus, the predictability is considered an important factor here. A traditional project management focuses on upfront planning where factors like cost, scope, and time are given importance.
Hence, the entire project is planned upfront without any scope for changing requirements.
To learn more about traditional project management here:
brainly.com/question/28139249
#SPJ4
Answer:
The ending balance of Allowance for Bad Debts account is $800
Explanation:
The computation of the ending balance of allowance for bad debt is shown below:
= Credit sales × uncollectible rate
= $40,000 × 2%
= $800
The estimated amount would be considered as an allowance for bad debts i.e $800, So no other amount would be come while computing the ending balance of Allowance for Bad Debts account.
However, the other information which is given in the question is not relevant. Hence, ignored it
Answer: B. Operational planning
Explanation: Blair, the production line supervisor engaged in
" operational planning " activities by creating specific employee work assignments and production schedules for coming weeks.
Operational planning is an activity of preparing plans by a unit in an organization, the plans are meant to state clearly the action and work plan the organization will take to achieve its goals and objectives which is set by management.
Answer:
Letter D is guess
Explanation:
Don't give out personal info, have a complex password and don't give it out to anyone, don't click on random pop up adds, and use a firewall
Answer:
The average job lateness for the sequence developed is 328 days
Explanation:
Given that the initial work day is base on day 275, the following is going to be the new sequence of the given jobs:
Job Due Date
A 318 5
B 317 3
C 320 8
D 327 16
E 364 40
Therefore, the average job lateness is calculated as follows:
(318+317+320+327+364)/5=328 Days