Answer:
the probability that the project will be completed in 95 days or less, P(x ≤ 95) = 0.023
Step-by-step explanation:
This is a normal probability distribution question.
We'll need to standardize the 95 days to solve this.
The standardized score is the value minus the mean then divided by the standard deviation.
z = (x - xbar)/σ
x = 95 days
xbar = mean = 105 days
σ = standard deviation = √(variance) = √25 = 5
z = (95 - 105)/5 = - 2
To determine the probability that the project will be completed in 95 days or less, P(x ≤ 95) = P(z ≤ (-2))
We'll use data from the normal probability table for these probabilities
P(x ≤ 95) = P(z ≤ (-2)) = 0.02275 = 0.023
Answer:
Step-by-step explanation:
D
A function assigns values of one set to another. The function that will represent g(x) is g(x)=(x-4)²+9.
<h3>What is a Function?</h3>
A function assigns the value of each element of one set to the other specific element of another set.
As it is given to us that we need to move the graph of the function 9 units up and 4 units towards the right. Therefore, the function that will represent the new location of the graph can be written as,
Hence, the function that will represent g(x) is g(x)=(x-4)²+9.
Learn more about Function:
brainly.com/question/5245372