1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
scoray [572]
3 years ago
6

Helpppppp! Is geometry

Mathematics
1 answer:
diamong [38]3 years ago
7 0

Answer:

Step-by-step explanation:

Nyu thanks, I can't be helped either

You might be interested in
Porfa ayudenme con este ejercicio.
Daniel [21]
D) La camisa roja y el pantalon negro
4 0
3 years ago
Read 2 more answers
Determine a25
posledela
I believe it’s 16/21 but I’m not sure.

4 0
3 years ago
Determine the nature of the roots:
malfutka [58]

Answer:

A.  2 distinct roots.

Step-by-step explanation:

2x^2 + 8x + 3 = 0

Finding the discriminant:

b^2 - 4ac = 8^2 - 4 * 2 * 3

=  64 - 24

= 40

The discriminant is positive but not a perfect square

So there are 2 distinct ,real, irrational roots.

5 0
2 years ago
What is the probability of rolling an odd number on the six-sided cube
tankabanditka [31]
It'd be a 50% chance
7 0
3 years ago
Read 2 more answers
mauricio estimates that the first module of the project could be completed in as few as 15 days or could take as many as 25 days
4vir4ik [10]

Answer:

<em>Most likely time, </em>according to PERT (Program evaluation and review technique).

Step-by-step explanation:

PERT is "a statistical tool used in <em>project management" (Program evaluation and review technique (2020), </em>in Wikipedia), and it is commonly used with CPM <em>(Critical Path Method)</em> to manage projects.

Inside PERT, there are different defined times to accomplished an activity in a project, that is:

  • An <em>optimistic time</em> or minimum time required to accomplished an activity, i.e., if everything goes better than normal, the activity is accomplished before expected.
  • A <em>pessimistic time, </em>a time quite the opposite to optimistic time.
  • A <em>most likely time</em>, or a time required to accomplished an activity if everything goes as expected or normally.
  • An <em>expected time</em>, an statistical estimation.

Considering the question, we have that the <em>time</em> when "the first module of the project could be completed":

  • "[...] in as few as 15 days"  is the <em>optimistic time</em>.
  • "[...] or could take as many as 25 days" is the <em>pessimistic time</em>.
  • "[...] but most likely will require 20 days" is the <em>most likely time</em>.

As a result, the <em>20-day estimate</em> is called the <em>most likely time</em> in the context of the PERT/CPM techniques.

3 0
3 years ago
Other questions:
  • Write an equation for each description. a number increased by 10 is 114
    9·2 answers
  • -5 / 6 - 1 / x equals negative two thirds​
    12·1 answer
  • In 10 minutes,a heart can beat 700 times.At this rate,in how many minutes will a heart beat 140 times? At what rate can. a heart
    15·1 answer
  • Given the diagram below, what is mD?
    11·2 answers
  • 5.<br>Find the LCM by the long division method:<br><br>(a), 18, 63, 78<br>​
    11·1 answer
  • A certain marathon has had a wheelchair division since 1977. An interested fan wondered who is​ faster: the​ men's marathon winn
    8·1 answer
  • Q2.The two triangles shown below are congruent by ?
    14·2 answers
  • PLZ HELP————————-///
    12·1 answer
  • Pls help........................
    7·2 answers
  • What is the value of x? Test is timed please help.
    12·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!