Answer:
14.77%
Explanation:
In this question, we apply the Capital Asset Pricing Model (CAPM) formula which is shown below
Expected rate of return = Risk-free rate of return + Beta × (Market rate of return - Risk-free rate of return)
= 4.97% + 1.40 × 7%
= 4.97% + 9.8%
= 14.77%
The (Market rate of return - Risk-free rate of return) is also called market risk premium and the same is shown in the answer
Answer: The loan was taken for 265 days.
We arrive at the answer as follows:
First we find the ratio of interest paid to the total loan amount to determine the interest rate:
Interest paid = $1,307
Loan Amount = $45,000

Since the interest rate calculated above is less than the annual interest rate at 4%, we conclude that the loan taken was for a period of less than one year.
We can determine the period for which the loan was taken as follows:
Let 'x' be the time for which the loan was taken.
We need to solve for x in the proportion below
0.04 : 365 :: 0.029044444:x
Solving we get,



Answer:
1. 4,200 units
2.7,200 units
Explanation:
<u>Prepare the Production Budget for January and February</u>
January February
Budgeted Sales 5,000 4,000
<em>Add </em>Budgeted Closing Stock 3,200 6,400
Total Production Needed 8,200 10,400
<em>Less</em> Budgeted Opening Stock (4,000) (3,200)
Budgeted Production 4,200 7,200
Budgeted Opening Stock for January comes from 80% of closing inventory from December !
Answer: B. producers typically enter a developing ecosystem before consumers.
Explanation: Succession can be described as the series of predictable changes that occur in a community over time.
During the process of Succession,producers typically enter a developing ecosystem before consumers.
Consumers need producers, this is because producers create food for themselves and also provide energy for the rest of the ecosystem.
Answer and Explanation:
The preparation of the factory overhead budget for August month is shown below:
Total budgeted direct labor $286,000
(5,500 × 4 hours × $13)
variable factory overhead 70%
Budgeted overhead $200,200 ($286,000 × 70%)
Add: Fixed overhead $179,000
Budgeted total factory overhead $379,200
Hence, the budgeted total factory overhead is $379,200