<span># of books = 4 ; original cost = 4*9=36; savings = 0.10*36= 3.60
</span>
<span># of books = 2 ;original cost = 2*20=40; savings = 0.20*40= 8.00
</span>
<span>Percent savings:
original total cost=$76
Total savings = $11.60
Percent savings: 11.60/76 = 0.1526..= 15.26%</span>
Answer:
Project A: $55,000 Project B: $50,800 Contractor should choose project A
Step-by-step explanation:
The expected value of the project is the sum of products of profit and its probability:
In thousands, ...
A: (50×0.6) +(80×0.3) +(10×0.1) = 30 +24 +1 = 55 . . . thousand
B: (100×0.1) +(64×0.7) +(-20×0.2) = 10 +44.8 -4 = 50.8 . . . thousand
__
The contractor should choose Project A based on the expected value of profit.
Hi:)
9m²/3m=3m
4m/3m=4/3
6/3m=2/m
3m-4/3-2/m
Hope i helped !!!