Answer:
a). You will have a total of $186,587.66 at the end of 42 years
b). You will have total of $78,816.64 at the end of 32 years
Explanation:
a). How much you will earn after 42 years
Step 1: Determine amount earned in 42 years
The total amount earned can be expressed as;
A=P(1+r)^n
where;
A=total amount earned
P=Initial investment amount
r=Annual interest rate
n=number of years of investment
In our case;
P=$5,000
r=9%=9/100=0.09
n=42 years
replacing;
A=5,000(1+0.09)^42
A=5,000(1.09)^42
A=186,587.66
You will have a total of $186,587.66 at the end of 42 years
b). Amount after 32 years
where;
P=5,000
r=9%=9/100=0.09
n=32 years
replacing;
A=5,000(1+0.09)^32
A=5,000(1.09)^32
A=78,816.64
You will have total of $78,816.64 at the end of 32 years
The answer is "wage structures"
GATT paved the way for the formation of many major trade agreements and institutions.
Answer:
The correct answer is option (D).
Explanation:
According to the scenario, the most appropriate answer is option (D) because value-based based sales-oriented business shows the concept that the seller provides the service of the more value as regarding the money charged to the customer.
While the other options are not correct because of the following reasons:
- Option (A) is not correct because retailing oriented business shows that the seller establishes a shop for the sale and the buyer chooses the product as he likes it.
- Option (B) is not correct because the market-oriented business shows the concept of selling according to the market needs.
- Option (C) is not correct because production-oriented business shows the concept of selling on the basis of production of the product.
Answer:
The correct answer is letter "A": can be used to estimate the projected cost of completing the project.
Explanation:
The Cost Performance Index or CPI measures the projected cost of work completed compared to the current cost spent. The CPI represents a ratio of earned value to actual cost. If the CPI is greater than one, the project is under budget. When the CPI equals one the planned and actual costs are equal. If the CPI is higher than one, the project is over budget.