Julli [10]
3 years ago
5

Which of the following is NOT an example of a business risk?

Business
1 answer:
olga55 [171]3 years ago
8 0

Answer:

a customer value proposition is not a business risk

You might be interested in
cost variance Tercer reports the following for one of its products. Direct materials standard (4 lbs. @ $2 per lb.) $ 8 per fini
maksim [4K]

Answer:

Total direct materials cost variance is $66,000 and it is favorable.

Explanation:

Actual cost = Actual Quantity × Actual Price

= 300,000  × $1.78

= $534,000

Actual cost with selling price = Actual Quantity  × Selling Price

= 300,000  × $2.00

= $600,000

The total direct materials cost variance is computed as:

Total direct materials cost variance = Actual cost with selling price - Actual Cost

= $600,000 - $534,000

= $66,000

It is favorable.

Working Note:

Actual Price per lbs = $534,000 / 300,000

= $1.78

8 0
3 years ago
Given that unit cost = $25, annual carrying charge = 10%, annual demand = 4000 units and ordering cost = $15 per order, the eoq
lutik1710 [3]
$2 per screw.<span>4000 units</span>
5 0
3 years ago
The S&amp;H Mercantile in Luther is the only game in town for a number of items, and tries valiantly to use only the storage spa
Artemon [7]

Answer:

A. The required order cost per lot is $0.388

B. The required order cost per lot is $0.9216

Explanation:

A. According  to the given data Given area of shelf space = 5 Ft * 4 Ft = 20 Sq. Ft

Let us covert it to Sq. inch

1 Ft = 12 Inches

Therefore , Area of shelf space = 20 *12 * 12 = 2,880 Sq. in

1 can of water takes 20 Sq inch of shelf space

Therefore no. of cans that the shelf space can hold = 2880 / 20 = 144 Cans

Now SH wants to store exact amount of shelf space without needing to store cans somewhere elseand hence this 144 cans becomes EOQ (Economic order Qty.)

Now we know EOQ = √(2KD) / h ----Eq. 1

EOQ = 144

K = Fixed ordering cost = ?

D = Annual demand = 8000

h = Holding cost = ?

C = Cost per can = $ 3

i = 10 % (Carrying cost as percentage of Unit cost)

h = i * C

h = 10 % * $ 3

h = $ 0.3

Substituting above in Eq. 1 and solve for K

EOQ = √ (2KD) / h

144 = √(2 * K * 8000) / 0.3

Squaring both sides we get

20,736 = (16,000 * K ) / 0.3

20,736 * 0.3 = 16,000 * K

K = 6220.8 /16000

K = $ 0.388 = Ordering cost per order

The required order cost per lot is $0.388

B.  Here EOQ remains same = 144  But other parameters change

K = Fixed ordering cost = ?

D = Annual demand = 27,000

h = Holding cost = ?

C = Cost per can = $ 12

i = 20 % (Carrying cost as percentage of Unit cost)  

h = i * C

h = 20 % * $ 12

h = $ 2.4

Substituting above in Eq. 1 and solve for K

EOQ =√(2KD) / h

144 =  √(2 * K * 27,000) / 2.4

Squaring both sides we get

20,736 = ( 54,000 * K ) / 2.4

20,736 * 2.4 = 54,000 * K

K = 49,766.4 /54,000

K = $ 0.9216 = Ordering cost per order

The required order cost per lot is $0.9216

4 0
3 years ago
Arabian Beauty Cosmetics borrowed BD 152.300 from the National Bank of Bahrain (NBB) for three years. If the quoted rate (APR) i
Tju [1.3M]

Answer: 12.47%

Explanation:

First convert the APR to the relevant periodic rate.

The compounding is done daily so the periodic rate is:

= 11.75%/365

Effective Annual rate is calculated by the formula:

= ( 1 + periodic rate)  ^ compounding period per year - 1

= ( 1 + 11.75%/365)³⁶⁵ - 1

= 12.47%

5 0
3 years ago
Deployment Specialists pays a current (annual) dividend of $1 and is expected to grow at 22% for two years and then at 5% therea
AleksAgata [21]

Answer:

The value of the stock = $19.64

Explanation:

According to the dividend valuation model, <em>the value of a stock is the present value of the expected future cash flows from the stock discounted at the the required rate of return.</em>

Year                     Workings                        Present value(PV)

1                 $1 × (1.22)  × 1.11^(-1)  =                     1.10

2                 $1 × (1.22)^2 ×(1.11)^(-2) =                1.21

3                 $1 × ((1.22)^2 × (1.05))/0.11-0.05) = 21.35 ( PV in year 2 terms)

PV (in year 0) of Year 3 dividend  = 21.35 × 1.11^(-2)

                                      = 17.33 (see notes)

<em>The value of the stock</em> = $1.10+ $1.21 + 17.3

                                      = $19.64

Notes:

<em>Note the growth applied to year 3 dividend gives the PV in year 2 terms. So we need to re-discount again to year 0.</em>

<em />

The value of the stock = $19.64

                                     

8 0
2 years ago
Other questions:
  • A #10 can yields 120 oz. of pineapple. they plan to give each guest an 8-oz. portion. they estimate there will be 240 guests. ho
    12·1 answer
  • Suppose that a firm in a competitive market is currently maximizing its short run profit at an output of 50 units. If the curren
    8·1 answer
  • Colombia has an absolute advantage in producing coffee relative to the United States.
    5·1 answer
  • Asset allocation refers to ________. A. the allocation of the investment portfolio across broad asset classes B. the analysis of
    7·2 answers
  • El Tapitio purchased restaurant furniture on September 1, 2021, for $45,000. Residual value at the end of an estimated 10-year s
    12·1 answer
  • A sedentary lifestyle is one that is characterized by high levels of physical activity.
    14·1 answer
  • Cala Manufacturing purchases land for $489,000 as part of its plans to build a new plant. The company pays $35,300 to tear down
    10·1 answer
  • Last year, Rec Room Sports reported earnings per share of $9.10 when its stock price was $282.10. This year, its earnings increa
    14·1 answer
  • If the government removes a tax on a good, then the price paid by buyers will
    14·1 answer
  • ______________ can arise from the estimation process or the stability of the project team. assumptions internal risks cost overr
    12·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!