i am edditing my post because i got the answer wrong
Answer:
The first one is you don't make eye contact with others. And the second one is false
Step-by-step explanation:
Based on the calculation, the perimeter of the horizontal cross-section is equal to 36.13 cm.
<h3>How to calculate the perimeter?</h3>
In this scenario, the resulting geometrical shape formed when the cut is made at the middle of the height of the trapezoid and then rotated is a circle.
<u>Given the following data:</u>
From the middle, the diameter of this circle is given by:
D = 1/2 (10 + 13)
D = 11.5 cm.
Now, we can calculate the perimeter:
Perimeter = πD
Perimeter = 3.142 × 11.5
Perimeter = 36.13 cm.
Read more on trapezoid here: brainly.com/question/4758162
#SPJ1
Answer:
Step-by-step explanation:
Given
Normal Hour = 32 hours
Overtime = Hours above 32
Rate for Overtime = 1.4 times normal rate
Earnings = $535.62
Required
Determine the normal hour pay
First, we need to determine the hours worked overtime.
This is:
The equation that binds all the parameters is:
This gives:
Solve for r
Answer:
<em>Most likely time, </em>according to PERT (Program evaluation and review technique).
Step-by-step explanation:
PERT is "a statistical tool used in <em>project management" (Program evaluation and review technique (2020), </em>in Wikipedia), and it is commonly used with CPM <em>(Critical Path Method)</em> to manage projects.
Inside PERT, there are different defined times to accomplished an activity in a project, that is:
- An <em>optimistic time</em> or minimum time required to accomplished an activity, i.e., if everything goes better than normal, the activity is accomplished before expected.
- A <em>pessimistic time, </em>a time quite the opposite to optimistic time.
- A <em>most likely time</em>, or a time required to accomplished an activity if everything goes as expected or normally.
- An <em>expected time</em>, an statistical estimation.
Considering the question, we have that the <em>time</em> when "the first module of the project could be completed":
- "[...] in as few as 15 days" is the <em>optimistic time</em>.
- "[...] or could take as many as 25 days" is the <em>pessimistic time</em>.
- "[...] but most likely will require 20 days" is the <em>most likely time</em>.
As a result, the <em>20-day estimate</em> is called the <em>most likely time</em> in the context of the PERT/CPM techniques.