Answer and Explanation:
a. The net long term capital loss would be $7,000
And, the net short term capital gain would be $14,000 ($21,000 - $7,000)
So as a result the overall net short term capital gain is $7,000
b. Since there is a loss arise from the personal residence of $28,000 so the blank would be filled by the amount i.e. $28,000 and the rest of the things would be alright.
Question: The question is incomplete. See the full question below and the answer.
You are an up-and-coming developer in downtown Seattle and are interested in constructing a building on a site you own. You have collected four bids from prospective contractors. The bids include both a cost ($millions) and time to completion (months):
Contractor Cost Time
A 100 20
B 80 25
C 79 28
D 82 26
The problem now is to decide which contractor to choose. B has indicated that for another $20 million, he could do the job in 18 months, and you have said that you would be indifferent between that bid and the original proposal. In talking with C, you have indicated that you would just as soon pay her an extra $million if she could get the job done in 26 months. Who gets the job? Explain your reasoning. (It may be convenient to plot the four alternatives on a graph.)
Answer:
See the explanation for the answer and find attached of the graph.
Explanation:
So we draw a regression line of Time vs Cost and best fit a curve based on the data given, given in the above figure. The four alternatives are marked in the figure as well. Our main objective is to reduce both time and cost, but that might not be possible So the best thing would be to look for alternatives which lie below the line. If C gets an extra million, then that point would come below the regression line, and it would be a better alternative than D, because for the same time we are getting the job done at a cheaper cost.
Also if B is paid extra 20 million, that point also comes below the regression line, and hence will be a better alternative than A because for the same cost again we are getting the job done earlier. We need to choose between B and C. Now in order to optimise both cost and time, we need to choose a point close to the middle point of the regression line segment in 1st quadrant. We see that C is much more closer to the middle point and hence seems like a better option.
So we choose C as our contractor if we consider B's alternative bid, but if we do not consider B's alternative bid and stick to the original one, we choose B as our contractor.
1 is because puppies are just the cuties thing ever.Also because animals are really sweet to human and they provide happiness and love so I would do the same for them plus I love to help all living thing
Answer:
$ 870,000
Explanation:
Given data:
The funds raised by the cancer society = $ 900,000
The amount that has been collected back = $ 600,000
The amount that is uncollectible = 10% of the remaining amount
i.e 10% of ( $ 900,000 - $ 600,000 ) = $ 30,000
Therefore,
the net amount of revenue the society should recognize during the current year from this pledge drive is calculated as:
= The funds raised by the cancer society - The amount that is uncollectible
or
= $ 900,000 - $ 30,000
or
= $ 870,000
Answer:
D) $123,000
Explanation:
Total Costs provided, based on activity based costing,
Wages and salaries = $360,000
Depreciation = $100,000
Utilities = $120,000
Other activity cost pool sharing for the above 3 activities
Wages and salaries = 10% = $360,000
10% = $36,000
Depreciation = 45% = $100,000
45% = $45,000
Utilities = 35% = $120,000
35% = $42,000
Total of other activities = $36,000 + $45,000 + $42,000 = $123,000
Final Answer
D) $123,000