Answer:
Reorder point necessary to provide 98% service probability is 1569 units
If the production manager is asked to reduce the safety stock of the item by 50%, the new service probability will be 84.7%
Explanation:
Data:
Weekly demand (<em>d</em>)= 300 units
Lead time (<em>L</em>)= 4 weeks
Standard Deviation (SD) = 90units
(A) To find reorder point.
-standard deviation (SDw) with lead time of 4 weeks =
x (90) = 180units
-98% probability is needed, use the formular NORMSINV (0.98) in Excel Spread sheet and get value of "z" to be 2.05
R = <em>d*L</em> + z*(SDw)
R = 300 x (4) + (2.05) x (180)
R = <u>1,569 units</u>
Note; determining the safety cost "SS"
SS = z * SDw = 2.05 x 180 = 369 units
for a 50% reduction, 369 x 0.50 = 184.5 ≅ 185 units
(B) now calculate "z" when safety stock is 185 units
SS = z * SDw
185 = z (180)
z = 1.02
In table, the corresponding probability value of 1.02 is <u>84.7%</u>