Answer:
The appropriated answer will be "$1,700,000".
Explanation:
Revenue understood by completion percentage = Design balance throughout progress = $200,000
The percentage completion throughout the whole year will be:
⇒ 
⇒ 
The cost incurred throughout the whole year will be:
⇒ 
⇒ 
⇒
($)
Now,
The total estimated cost of the project at the end the year 2021 will be:
⇒ 
⇒
($)
Answer:
D. Both B and C
Explanation:
Based on the information provided within the question it can be said that you must go to The Building Codes and Building Officials Conference of America. This is where every company must go in order receive the guidelines of the materials that are approved by the government for all development procedures including construction, electrical wiring etc.
Answer:
Part 1
$1,422,940
Part 2
$331,480
Explanation:
cost of the land calculation
Purchase Price $1305000
Cost to tear down building $121000
Sale of Salvages ($8400)
Leagl fees $5340
Total $1,422,940
The cost of the land that should be recorded by Wilson Co. is: $1,422,940
cost of the building calculation
Architect's fees $47000
Insurance $3900
Liability insurance $4200
Excavation cost $15480
city for pavement $9900
Borrowing Costs $251000
Total $331,480
The cost of the building should be recorded by Wilson Co. is $331,480