Answer:
<h2>8</h2>
Step-by-step explanation:

Answer:
Sharika needs 2.5 days to finish the remaining work
Step-by-step explanation:
Sharika can do a work in 6 days palkey can do it in 8 days
Then the amount of work sharika can do in 1 day = 1/6
And the amount of work palkey can do in 1 day = 1/8
The amount of work both of them can do together in 1 day = 1/6 + 1/8
= 7/24
The amount of work both of them can do together in 2 day = (2× 7/24)
= 7/12
Since Palkey left the work,the amount of
work remaining for Sharika to do alone = (1 - 7/12 )
= 5/12
The number of days Sharika take to finish the remainig work. = (5/12 ÷ 1/6 )
= 5/2 days
Therefore, Sharika needs 2.5 days to finish the remaining work.