Solution: Estimated time for the work is 40 hour work week.
Estimated payment to 3 laborers working 40 hours at cost $14 per hour is:
$1680
Estimated payment to 6 masons working 40 hours at cost $24 per hour is:
$5760
Estimated cost of material = $3143
Contractor wishes to make a profit of $500
Therefore, the mathematical expression that will give the estimated cost of the job is:
The estimated total cost is:
Cost =$11083
The simplest fraction is 1/16
How did bill spend longer .. days ... ? what
Nellie has to calculate the price per pound for every bag.
1) 2.52 / 3.5 = 0.72 $/lb
2) 5.40/7.5 = 0.72 $/lb
3) 7.92/11 = 0.72 $/lb
Then, price per pound is the same for any bag. There is no advantage of purchasing one or other, given that she can store any quantity.
The answer of the question is C