Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
Answer:
Hello! Mizuki here to help
The correct answer would be B
Step-by-step explanation:
Number of people who didn't get flu and weren't vaccinated:115
Answer:it didnt
Step-by-step explanation:
Answer:
its a)the first sequence is geometric bc of the common ratio of 2. the second sequence is arithmetic bc of the common difference of 7.
Answer:
round to 1
Step-by-step explanation:
it is closest to 1 so it wouldnt make sense to round to a number farther away