A construction manager needs 12 workers to complete a building project in 54 days, we can write;
12 workers = 54 days
T find the number of workers needed to complete the same project in T days, we will write;
x workers = T days
Divide both equations
12/x = 54/T
Cross multiply
12T = 54x
x = 12T/54
x = 2T/9
Hence the number of workers needed to complete the same project in T days is 2T/9 workers