Answer:
1. groups costs into meaningful buckets that are then distributed based on the activity or product they support.
Explanation:
Activity based costing basically categorizes various overheads into different activities, that leads to charge of overheads based on different activities.
In this manner overheads that shall be charged on some standard products based on the activities involved is charged accordingly, and not based on standard overhead allocation rate.
Basically the overheads are divided into various activities and then distributed to each product based on the volume of activity in the manufacturing process of such activity.
Place your car in "park."
Defend you against approaching traffic.
When a vehicle collision occurs, it might be stressful, but it's crucial to keep in mind that your safety is always the top priority. Immediately upon being involved in a collision, keep in mind the following advice:
Verify your own health and the health of any passengers.
If you require medical asisstance or can't move your car, call "911" and follow the operator's instructions.
You should relocate to a safe area (such as the closest shoulder, the median, or the rightmost lane of the road) before exiting your car to examine the situation if it is still operational and neither you nor any of your passengers have been hurt.
to know more about property damage
brainly.com/question/4539405
#SPJ4
Answer:
good morning I hope you l I e for the update on the answer to the answer to the question on the answer to the question on the answer to the question on the answer to the question on the
Answer: $2.33
Explanation:
The unit contribution margin that is required to attain the profit target will be calculated thus:
= (Fixed cost + Desired profit) / Estimated units
= ($225,000 + $125,000) / 150,000
= $350,000 / 150,000
= $2.33
Therefore, the unit contribution margin is $2.33
Answer:
d.$72 per machine hour
Explanation:
Predetermined overhead rate = Budgeted Overheads ÷ Budgeted Activity
therefore,
Predetermined overhead rate = $11,742,000 ÷ 164,000
= $71.598 or $72
The predetermined overhead rate based on machine hours is $72 per machine hour.