Answer:
$4,038
Explanation:
Present value (PV) is the current value of a future sum of money or stream of cash flows given a specified rate of return. Future cash flows are discounted at the discount rate, and the higher the discount rate, the lower the present value of the future cash flows.
Present Value = Future Value x (1/ ( 1 + interest rate ) ^ number of periods)
Present Value = 6,000 x (1/ ( 1 + 0.08) ^ 5)
Present Value = 6,000 x 0.68058
Present Value = $4,038
These costs called as Transferred costs.
<h3><u>
Explanation:</u></h3>
The costs that are accumulated during the time of upstream production process in a firm refers to Transferred costs. These are associated with the goods that are transferred to the next department of a business from one department. With this product there will be a continuation of the production process.
These are semi finished goods that are transferred for the purpose of continuing the production process. When these units are moved form the processing department to the next department, these transferred cost will be transferred from one work in process account to the next account.
Answer: The answer is provided below
Explanation:
Adjusting entries are the entries that are passed at the end of the year. They are passed to adjust the account so as to make them follow the matching principle.
In the calculation attached, it should be noted that the salary expenses was calculated as the amount earned per day by the number of days. This is:
= $800 × 5
= $4000.
The necessary journal has been attached
Answer:
c) finish-to-start; start-to-start
Explanation:
Project dependencies are the time relationships between a predecessor and a successor in project management. In other words, these dependencies describe which activity among the two needs to start earlier or later and when it needs to start or finish compared to the other one.
The most common type of dependency in all projects (no matter the nature or industry) is the finish-to-start one, where the activity A needs to be completed before activity B starts, e.g. base nail polish has to be put before the top coat gets put on the nails.
The second most common type of dependency is the<em> start-to-star</em>t one, where two activities need to start at the same time. This is common for activities where synchronization is paramount.