Answer: 30.6
Step-by-step explanation: she worked 30.6 hours be cause if you think 36 of 15% it is 30.6 hours she worked
Answer:
10 days
Step-by-step explanation:
We are given that
Each person takes 56 days
7 painters take time=
painter days
In first 6 days , 7 painters take time=
painter days
After 6 days , 28 volunteers are added then,
Total persons=28+7=35
Now, remaining days=392-42=350
Therefore, number of days are required before the painting of the king of rock 'n' roll is completed=
days
Hence,10 more days are required before the painting of the king of rock 'n' roll is completed
Answer: I think its b
Step-by-step explanation:
In order to do this, we would use order of operations. First, Parentheses, which is division with fractions, so we would do KCF,keep it, change it, flip it. keep the first fraction, change the operation to multiplication, then flip the next fraction, making it -7/9 x 3/1. the answer would be -2.33. multiply that by -2, and you would get -4.66, which is your answer. PLEASE MARK BRAINLIEST IF HELPFUL! :))
Answer:
Area of triangle = ½ × base × height
Step-by-step explanation:
(A = ½ × b × h)
This formula is mainly used to find the area of the triangle.