Answer:
Cost variance= 7 unfavorable
Explanation:
Giving the following information:
Each bat requires 1 kg of aluminum at $18 per kg and 0.25 direct labor hours at $20 per hour. Overhead is assigned at the rate of $40 per direct labor hour. Assume the actual cost to manufacture one metal bat was $40.
Estimated cost= 18 + 0.25*20 + 0.25*40= 33
Actual cost= 40
Cost variance= 7 unfavorable
There is 1000 tickets and you have one so you have 1 in a 1000 chance
Answer:
hi you seem like a really nice persen sorry
Explanation:
Answer:
C. calculating the total output for Portugal
Explanation:
- Aggregate demand can be thought as the total amount of products that are demanded by individuals in an economy, in a certain period of time.
- It is a way of measuring the total output of goods demanded in a territory, periodically.
- Because in equilibria, aggregate demand must equal aggregate supply, thinking about total output (produced and demanded) is correct.
- Because <u>it has to do with all the goods that are demanded,</u> options A and B are not suitable.