Answers:
Correct answer:
1. Investment
2. Trade-off of present for future benefit
Incorrect answers:
1. The only possible decision
2. The consumption of consumer goods.
Answer:
$133,600
Explanation:
Straight line depreciation expense = (cost of asset - salvage value) / number of year
Cost of asset = $340,000 + $14,000 + $40,000 = $394,000
($394,000 - $60,000) / 5 = $66,800
The amount of accumulated depreciation at December 31, 2018 = $66,800 x 2 = $133,600
Answer:
The correct answer is (B)
Explanation:
Producers are influenced by the benefits and profits they hope to pick up from the products or administrations in a free market economy. The idea of producers is to create goods and services and sell them at maximum profits because they feel consumer will buy their products because they need them. A profit motive is generally beneficial to the overall economy of the country. It is expected to give a motivating force to create productivity and development.
Conversion cost is defined as the sum of direct labor costs and manufacturing overhead costs. It is the manufacturing cost needed to convert raw materials to a product. From the information given above, the conversion cost is the summation of direct material costs, direct labor costs and factory overhead costs.
$3000,000 + 7,000,000 + 5,000,000 = 15,000,000
Therefore, the conversion cost is $15,000,000.
Answer:
A) Using a change management system to influence performance
Explanation:
First of all, since the change was proposed by the customer, any delay in the construction project caused by their new request should not trigger the damage clause.
The contractor should use a change management system so the existing baseline is not altered by the delay. A change management system is responsible for managing all the changes that might occur during the project's inception until its completion. It is important that all changes or alterations to the original schedule are properly recorded and authorized (in this case to prevent the damage clause).
By using the change management system, the organization has a standardized methodology for handling changes in the project's schedule. This way any negative impact can be reduced.