miss Akunina [59]
4 years ago
12

Anybody, please answer this for me. I'm not good at mathematics

Mathematics
1 answer:
Lostsunrise [7]4 years ago
3 0
Well, its kind of obivious that 2x + 4 stands out, but I think you are asking why. Whereas all other lines shown are vertical or horizontal, 2x+4 is diagonal. 
You might be interested in
In the diagram below, BC−→− bisects ∠FBE
nirvana33 [79]

Answer:

<em>m∠EBC = 34° </em>

Step-by-step explanation:

m∠DBC = m∠DBE + m∠ EBC

m∠DBC - m∠DBE = m∠EBC

(12x - 3)° - (5x + 12)° = (3x + 13)°

12x - 5x - 3 - 12 = 3x + 13

4x = 28

x = 7

<em>m∠EBC </em>= (3(7) + 13)° <em>= 34° </em>

7 0
3 years ago
Please help me do number One
valentina_108 [34]
What are the options on top take a picture of those then I will be able to help you
4 0
3 years ago
What is a number with one or more digits to the right of the decimal point called?
velikii [3]

Answer:

hm if it were in fraction form it would be called a mixed number but if not the it would be either tenths hundredths thousandths these three would be the most common of them all

Step-by-step explanation:


7 0
3 years ago
Read 2 more answers
M5_A3. The expected project completion time for the construction of a pressure vessel is 18 monthsand the project variance is 7.
snow_tiger [21]

Answer:

a) 0.3520

b) 0.9884

c) 0.1292

d) 0.1292

e) 0.7648

Step-by-step explanation:

Problems of normally distributed samples can be solved using the z-score formula.

In a set with mean \mu and standard deviation \sigma, the zscore of a measure X is given by

Z = \frac{X - \mu}{\sigma}

After finding the Z-score, we look at the z-score table and find the p-value associated with this z-score. This p-value is the probability that the value of the measure is smaller than X.

In this problem, we have that:

The expected project completion time for the construction of a pressure vessel is 18 months. So \mu = 18.

And the project variance is 7. The standard deviation is the square root of the variance, so \sigma = \sqrt{7}.

a) What is the probability that the project will require at least 19 months?

The pvalue of the zscore of X = 19 is the probability that the project will require less than 19 months. So the probability that the project will require at least 19 months is the subtraction of 1 by this pvalue.

Z = \frac{X - \mu}{\sigma}

Z = \frac{19 - 18}{\sqrt{7}}

Z = 0.38

The pvalue of Z = 0.38 is 0.6480.

So the probability that the project will require at least 19 months is 1 - 0.6480 = 0.3520.

b) What is the probability that the project will be completed within 24 months?

This is the pvalue of the zscore of X = 24.

Z = \frac{X - \mu}{\sigma}

Z = \frac{24 - 18}{\sqrt{7}}

Z = 2.27

The pvalue of Z = 2.27 is .9884. This means that the probability that the project will be completed within 24 months is .9884.

c) What is the probability that the project will require at least 21 months?

Same logic as a). We find the pvalue of the zscore of X = 21, then we subtract 1 by this value.

Z = \frac{X - \mu}{\sigma}

Z = \frac{21 - 18}{\sqrt{7}}

Z = 1.13

The pvalue of Z = 1.13 is 0.8708.

So the probability that the project will require at least 21 months is 1 - 0.8708 = 0.1292.

d) What is the probability that the project will be completed within 15 months?

Same logic as b). This is the pvalue of the zscore of X = 15.

Z = \frac{X - \mu}{\sigma}

Z = \frac{15 - 18}{\sqrt{7}}

Z = -1.13

The pvalue of Z = -1.13 is .1292. This means that the probability that the project will be completed within 15 months is .1292.

e) What is the probability that the project will take between 16 and 24 months to complete?

This is the pvalue of Z = 24 subtract by the pvalue of Z = 16.

In b), we found that the pvalue of Z = 24 is .9884

Now we find the pvalue of Z = 16

Z = \frac{X - \mu}{\sigma}

Z = \frac{16 - 18}{\sqrt{7}}

Z = -0.76

The pvalue of Z = -0.76 is 0.2236

So the probability that the project will take between 16 and 24 months to complete is 0.9884 - 0.2236 = 0.7648

8 0
4 years ago
If y=5x-3 and 3x-y=-1, what is the value of y
Svet_ta [14]
Well if you make them both equal to y I got...
Y=-3x+1
Y=5x-3
But I don't think you can find it without the y since they are different variables. Like I know -3x and 5x are the slopes and 1 and -3 are the y intercepts but I'm stuck after that. Sorry if that wasn't any help.
Hope I helped.
3 0
3 years ago
Read 2 more answers
Other questions:
  • Someone help me figure out the equation for this please
    6·1 answer
  • Many grandparents invest in the stock market for their grandchildren's college fund. Eighteen years ago, your grandparent jumpin
    13·1 answer
  • Write the equation for the circle in standard form<br><br> x2 + y2 - 12x - 12y + 36 = 0
    6·1 answer
  • When partitioning a line segment, what does the rational form of the ratio 2:3 look like?
    14·2 answers
  • Which equation has an a-value of 1, a b-value of –3, and a c-value of –5?
    13·2 answers
  • The length of jade's garden is 4w
    7·2 answers
  • Jerry is charged for $2 for every day he is late paying his cable bill. Which integer correctly shows how much Jerry owes if he
    9·1 answer
  • What percent is 3 is 1?Write ur answer as a fractional percent.Make sure your answer is fully reduced.:)​
    9·1 answer
  • jeremy swims at a rate of 1/3 miles every 1/6 hour. at this rate, how many miles will he swim in one hour?
    12·1 answer
  • REVIEW
    12·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!