Answer: $1.50
Explanation:
Based on the information given in the question, we are informed that the variable cost of each box is $1.50 and usually has a contribution margin of $0.80 per box.
We should note that the minimum transfer price that the box division should find as acceptable will be the relevant cost. In this case, the relevant cost is given as $1.50 pee box and therefore, the minimum transfer price will be $1.50.
Answer: Decrease, Increase, Price flexibility.
Explanation: According to classical economics, a decrease in aggregate demand causes the price level to DECREASE in the long run. On the other hand, an increase in aggregate demand causes the price level to INCREASE in the long run. These changes occur because of PRICE FLEXIBILITY.
In a flexible market the forces of demand and supply determines the prices of commodities in the market.
As the demand Falls the prices also fall as the demand rises the prices of commodities also rises.
Answer:
Expense & revenue summary a/c (credit balance) = $3500
Explanation:
1. Dr Expense & revenue summary 52500
Cr Sales discount 1500
Cr Sales return & allowance 3000
Cr Depreciation expense 25000
Cr Salaries expense 23000
(Close expenses to expense & revenue summary a/c)
2. Dr Sales 56000
Cr Expense & revenue summary 56000
(Close sales to expense & revenue summary a/c)
3. Dr Expense & revenue summary a/c 3500
Cr Retained earning a/c 3500
(To close expense & revenue summary a/c)
4. Dr Retained earning 2000
Cr Expense & revenue summary 2000
(Close dividend to expense & revenue summary a/c)d
Answer:
The NPV from opening the branch office is negative ( -$106668.08). Thus the branch office should not be opened.
Explanation:
The decision to open the branch office will be taken based on the NPV provided by opening of the branch office. If the NPV of a project is positive based on the required rate of return used as a discount rate fro cash flows, the investment is worth undertaking.
The net present value (NPV) for a project can be calculated as,
NPV = CF1 / (1+r) + CF2 / (1+r)² + ... + CFn / (1+r)^n - Initial Outlay
Where,
- r is the appropriate discount rate
- Initial Outlay is the Initial cost of the project
- CF represents cash flows from the project
As the required return is 16%, we will take this as the appropriate discount rate.
NPV = 45000 / (1+0.16) + 120000 / (1+0.16)² + 150000 / (1+0.16)³ +
150000 / (1+0.16)^4 + 150000 / (1+0.16)^5 - 485000
NPV = - $106668.08
As the NPV from project is negative at a required return of 16%, the project should not be under taken and the branch office should not be open.
Complete Question:
Company uses the percent-of-sales method to estimate uncollectibles. Net credit sales for the current year amount to $500,000, and management estimates 2% will be uncollectible. The amount of expense to report on the income statement was $8,000. The Allowance for Uncollectible Accounts prior to adjustment has a credit balance of $2,000. The balance of Allowance for Uncollectible Accounts, after adjustment, will be
Answer:
The balance of Allowance for Uncollectible Accounts, after adjustment, will be
$10,000
Explanation:
a) Data and Calculations:
Net credit sales = $500,000
Uncollectible estimate = 2% of net credit sales
Uncollectible Accounts expense = $8,000
Allowance for Uncollectible Accounts = $2,000 before adjustment
Allowance for Uncollectible after adjustment = $500,000 * 2% = $10,000