Answer:
$355 unfavorable
Explanation:
Budgeted supplies cost was [$1,860 + (635 frames x $ 11)] = ($1,860 + $6,985) = $8,845
Actual supplies cost was $9,200, so the variance was = budgeted cost - actual cost = $8,845 - $9,200 = $355 unfavorable
Since the actual supplies cost was higher than the budgeted supplies cost, then the variance must be unfavorable (because more money was spent than expected).
When evaluating a supplier using the integrated supplier scorecard, most are reevaluated on quality of their products, cost of the product, how quickly the items are able to be deviled and the flexibility the supplier has when the organization needs supplies. The scorecards allow the company to make sure they are doing and receiving the best items from their suppliers on each different level.