Answer:
He will run 31.6 miles in two weeks.
Step-by-step explanation:
6 days a week = 2.3 miles
6 days · 2 weeks = 12 days total running 2.3 miles
1 day a week = 2 miles
1 day · 2 weeks = 2 days total running 2 miles
(12 · 2.3) + (2 · 2)
27.6 + 4
31.6 miles
Answer:
The solution is given below:
Step-by-step explanation:
The computation is shown below:
= 19 + 7 divided by 2 - 5
= (19 + 7) ÷ (2) - 5
= 26 ÷ 2 - 5
= 13 - 5
= 8
Hence, after solving this the value would be 8
Therefore it is equal to the 8
Hence, the given statement is true
Answer:
Equal 2 payments of 17.50$.
Work=speed times time (my equation to help me figure it out)
ok, 10 men take 84 days to complete a job
therefor, each man completes 1/10 of the job in 84 days
each man does 1/840 of the job per 1 day
so, if we had 5 more, or 15 men
15 times 1/840 times xdays=1 job complete
15/840 times xdays=1job
times both sides by 840/15
xdays=840/15
xdays=56
56 days it would take
Answer:
Step-by-step explanation: