I think the most appropriate answer would be "inelastic demand". As the demand doesn't decrease significantly high and the cost of gasoline doesn't increase significantly increase that high.
(Inelastic demand is the the demand of a product does not changes too much/vigorously, as compared to elastic demand.)
I hope it helped you!
Answer:
The correct answer is the option D: Total project costs are the lowest.
Explanation:
To begin with, when it comes to the business field and the management area, the "project duration" refers basically to the characteristic that the project management has regarding the duration of it, very commonly expressed in terms of working units like hours, days, weeks, months or years for example. Moreover, there are three major types of project duration that are: "Estimated Project Duration", "Actual Project Duration" and "Remaining Project Duration". And to end up, the point where the duration of the project is opmital is when the total project costs are the lowest of all.
Answer:
The correct answer is (B) Price.
Explanation:
The price is a marketing variable that comes to synthesize, in a large number of cases, the commercial policy of the company. On the one hand, we have the needs of the market, set in a product, with certain attributes; on the other, we have the production process, with the consequent costs and profitability objectives set. That is why the company must be in charge, in principle, of setting the price it deems most appropriate.
For the potential customer, the value of the product is expressed in objective and subjective terms, since it has a very particular scale when computing the different attributes of which it is composed, hence the denomination of expensive or cheap it gives them. However, for the company the price is a very important element in its marketing mix strategy, along with the product, distribution and promotion.
Answer:
$16.66
Explanation:
Data provided
Direct material = $55,870
Direct labor hour = 475
Wage rate = $11
Machine hour = $556
Number of units = 4,100
Overhead rate = $13
The preparation of job sheet is shown below:-
Direct Material $55,870
Add: Direct Labor $5,225
( 475 × $11)
Overhead $7,228
($556 × $13)
Total $68,323
Number of units 4,100
Cost per unit $16.66
($68,323 ÷ 4,100)
<span>If the primary key of the workshop offerings table contains the primary key for both the workshop table and account table, there is a many-to-many relationship between accounts and workshops.
</span><span>A </span>one-to-many relationship<span> includes the </span>primary key of<span> the “</span>one<span>” table as a foreign </span>key<span> in the “</span>many<span>” table. </span>