Answer:
Debit : Rent Expense $1,660
Credit : Prepaid Rent $1,660
Explanation:
The January 31 adjusting entry for rent expense would include a Debit to Rent Expense and Credit to Prepaid Rent - Asset Account at an amount of $1,660.
Calculation :
Rent Expense = 1/12 x $19,920 = $1,660
Answer:
The answer is $38,500
Explanation:
Operating activities: Cash generated or used to run the day-to-day business operations.
Investing activities: Cash used for investing in assets like securities, bonds, equipment, or proceeds from these assets.
Financing activities: Cash generated from loan and/or payments made to reduce loan balances
Ending cash balance = Net Cash from operating activities + net cash from investing activities - net caash from financing activities + Beginning cash balance
Ending cash balance = $35,500 + $13,000 - $16,500 + $6,500
$38,500
Answer:
C. The legal system does not necessarily facilitate or stabilize commercial practice.
Explanation:
The government of the United States is a federal system in nature. It has a written system and a common law legal system. The "legal system" of American is based on the system of federalism or the decentralization system.
The legal system for America on the other hand is for interpreting and enforcing the law. Advance development in the political and legal system may increase the risk of the country. Thus the legal system of America does not facilitate or the stabilize any commercial practice in america.
Answer:
Compounding formula would be used here which is as under:
Future Value = Present value * (1+r)^n
FV = (PV is $2000) * ( 1 + 4%)^ 3 number of years
Remember that r is the return that is 4% that Sarah Jones will receive.
So
FV = $2250
So this is the amount that she will receive after three years. I would recommend her to invest in ordinary shares (take higher risk for higher return) so that she is able to buy a better car.
Full question attached:
Answer attached
Answer and Explanation:
ES= earliest start time
LS=latest start time
EF= earliest finish time
LF= latest finish time
in calculating earliest start time, we look at predecessor to the task, for example c has a predecessor of A and so ES would be after A=3.in calculating our earliest start time and latest finish time we have used the forward pass and backward pass method respectively. The forward pass method uses the latest of the predecessors earliest finish in calculating ES while the backward pass method uses the earliest of the successors latest start(LS)in calculating latest finish(LF)
EF=ES+time
LS=LF-time
slack=LF-EF
The Critical path is ADEG identified by zero slacks
project duration is equal to duration of critical path equal to 15