The easiest function available in MS Access to begin collecting data quickly is to use a pre-designed Template.
<h3>What is
pre-designed Template in MS Access?</h3>
Basically, the Ms Access is a database app that helps to store information for reference, reporting and analysis.
The pre-designed Template makes collection of data faster because the query, tables are already designed for instant use.
Hence, the Option B is correct since the easiest function available in MS Access to begin collecting data quickly is to use a pre-designed Template.
Read more about MS Access
<em>brainly.com/question/24643423</em>
A. correct me if im wrong
Answer:
Misstatement is referred to as errors in the presentation of financial information that could lead to wrong decision by the users
Explanation:
Occurrence : Issuing of dummy invoices for sales that did not occur
Completeness: Sales invoice were not fully recorded due to omission or misplacement
Authorization: Sales are not approved by the responsible manager. No authorized signature
Accuracy : Casting of sales figure on the register is not correct.
Cutoff : Sales are not recorded in the proper accounting period. January sales being recorded in the previous year account.
Classification : Grants being wrongly recorded as revenue
Presentation : Exaggerated revenue.
The precedence diagram for the problem above is attached. See the definition of a precedence diagram and the probability calculations below.
<h3>What is a precedence Diagram?</h3>
A precedence diagram is an optical or graphical representation tool that displays a project's activities.
<h3>
What is the probability of finishing the project by the 24th day or less?</h3>
Recall that:
z = (Specified Time - Path's mean)/Path's Standard Deviation.
Hence for z₂₁
(21 − 20.5)/1.118 = 0.447 ≈ 0.45.
Hence the probability is: P(Z<0.45) =0.6736
(21 − 21.5)/1.344 = −0.3721 ≈ −0.37
Hence the probability is: P(Z<-.37) = 0.3557
(21 − 19.5)/.726 = 2.066 ≈ 2.07
Hence the probability is: P(Z<2.07) = 0.9808
Following through on the above, the project will be finished in less than 21 days is given as:
P = 0.23499920921
P ≈ 0.2350
Learn more about Probability at:
brainly.com/question/24756209