Answer:
the first one
Step-by-step explanation:
A graph showing the Earliest Start Times (EST) for project tasks is computed left to right based on the predecessor task durations. For dependent tasks, the earliest start time will be the latest of the finish times of predecessor tasks.
The first graph appears to appropriately represent the table values, using edges to represent task duration, and bubble numbers to represent start times.
The second graph does not appropriately account for duration of predecessor tasks.
The third graph seems to incorrectly compute task completion times (even if you assume that the edge/bubble number swap is acceptable).
Answer:
c
Step-by-step explanation:
Yes and the correct one is A
Answer:
True
Step-by-step explanation:
The size of the vertex cover is atleast twice the size of the maximum edge. Vertex must contain atleast one vertex from the matched edge. Vertex are never the strong dual solutions of each other.
G, 7 is the flat rate price you have to pay and 3.50 is the price for rides since we don’t know the number of time he will ride we will have to times 3.50 to the amount of times he go’s on a ride